Week 6 – Closing A Project – Shuffle Q/A 4

49. Fill in the blank: A retrospective is an opportunity for _____.

  • feedback and lecture
  • criticism and collaboration
  • planning and introspection
  • reflection and improvement

50. A project manager describes the purpose and process of a project in their closeout report. What section are they writing?

  • Open items
  • Key accomplishments
  • Executive summary
  • Lessons learned