53. During the execution phase, an issue arises that will cause the project's costs to overrun the budget. How can the project manager address the issue?
- Ask your team to work more hours to meet timelines
- Document the issue and move forward
- Make a mental note to discuss in the retrospective
- Escalate the issue to leadership
54. As a project manager, you ensure the team is accomplishing the necessary tasks to hit target dates along the way. What item are you tracking?
- Progress towards milestone
- Team members planned PTO
- Project proposal
- Stakeholder options
55. During the project execution phase, what chart can you use to illustrate how a project should evolve over time to your stakeholders and team members?
- Burndown chart
- Roadmap
- Project status report
- Gantt chart
56. How does a change request form differ from an escalation email?
- Change request forms help teams manage proposed changes; escalation emails enlist leadership to remove obstacles, reinforce priorities, and validate next steps
- Change request forms enlist leadership to manage proposed changes; escalation emails help teams remove obstacles, reinforce priorities, and validate next steps
- Change request forms help teams remove obstacles, reinforce priorities, and validate next steps; escalation emails enlist leadership to manage proposed changes
- Change request forms enlist leadership to remove obstacles, reinforce priorities, and validate next steps; escalation emails help teams manage proposed changes